How Long Does it Take to Install an EV Charger?

The time required to install an EV charger at home can vary based on several factors, including the type of charger, the complexity of the installation, and the existing electrical infrastructure.

Here’s a breakdown of the typical installation process and timeframes and the factors influencing installation time

Type of EV Charger

Level 1 Charger: Typically takes the least time as it usually involves plugging into a standard 240-volt outlet. If you have an existing outlet near your parking area, installation can be as quick as 1-2 hours.

Level 2 Charger: Requires a dedicated 240-volt circuit and often involves more extensive electrical work. Installation time can range from 3 to 8 hours.

DC Fast Charger: Primarily used for commercial or high-capacity settings and requires significant electrical infrastructure. These installations can take several days due to the complexity and power requirements.

Electrical Panel & Circuit Requirements for EV Charger

Existing Capacity: If your electrical panel has sufficient capacity and space for a new breaker, this simplifies the process.

Panel Upgrades: Upgrading the panel or adding a new sub-panel can add several hours or even days, depending on the scope of work.

Distance and Cable Routing

Proximity to Electrical Panel: The closer the charger is to the main electrical panel, the less time it will take to run wiring and conduit.

Complex Routing: If the wiring needs to be routed through walls, ceilings, or underground, this can add to the installation time.

Permitting and Inspections

Permits: Obtaining permits may take time, but actual installation work often proceeds quickly once permits are secured.

Inspections: Scheduling and completing inspections can add to the overall timeframe, especially if they need to be done before the installation can proceed or be completed.

Charger Features and Setup

Basic Installation: Simple wall-mounted chargers with straightforward electrical connections take less time.

Advanced Features: Chargers with additional features like Wi-Fi connectivity or load management systems may require more time to configure and test.

Professional vs. DIY Installation

Professional Installation: Typically quicker and more reliable. Experienced installers can efficiently handle the complexities and ensure compliance with safety standards.

DIY Installation: May take longer if you are unfamiliar with electrical work and have to spend time troubleshooting or learning about the installation process.

Typical Timeframes for Installation

Level 1 Charger:

Installation Time: 1-2 hours

Requirements: Simple plug-in to a standard outlet; minimal electrical work needed.

Level 2 Charger:

Installation Time: 3-8 hours

Requirements: Installing a 240-volt circuit, mounting the charger, running cables, possibly upgrading the electrical panel.

DC Fast Charger:

Installation Time: Several days

Requirements: Extensive electrical infrastructure, possible site modifications, high-capacity electrical connections.

Steps in the Installation Process of an EV Charger

Initial Assessment:

Time: 1-2 hours

Activities: Site visit by an electrician to evaluate your electrical system, discuss installation options, and provide a quote.

Permitting and Preparation:

Time: Variable, from a few days to a couple of weeks depending on local requirements.

Activities: Obtaining necessary permits and preparing the installation site.

Actual Installation:

Time: 3-8 hours for Level 2 chargers (as detailed above).

Activities: Installing and wiring the charger, setting up the dedicated circuit, mounting the unit, and connecting to your home’s electrical system.

Testing and Commissioning:

Time: 1-2 hours

Activities: Testing the installation to ensure the charger works correctly, configuring any smart features, and providing user training.

Conclusion

The time to install an EV charger at home can range from a couple of hours to several days, depending on the charger type, electrical work required, and site-specific factors. For a smooth and efficient installation, it’s advisable to work with a professional who can handle the complexities and ensure compliance with safety standards.

Further Guidance

 Are Electric Cars Cheaper to Run?  

How Much Does it Cost to Charge an Electric Car?

How Long Does it Take to Charge an Electric Car?

How Much to Install EV Charger?

How Long Does it Take to Install an EV Charger?

OZEV Grants

Is it Worth Installing an EV Charger at Home?

Can You Install EV Chargers Outside?  

Can I Install Fast EV Charger at Home?

Can Any Electrician Install an EV Charger?

Can I Install an EV Charger Myself?

Do I Need a Permit to Install an EV Charger?

Do I Need Permission to Install an EV Charger?

Get an EV Charger Supplied & Installed in 3 Easy Steps

Step 1 - Quote

Give us a call or reach out to us online and we will provide you a free, non obligated quotation that suit both your budget and your needs.

Step 2 - Install

Our qualified electricians handle the entire installation process with precision and care. From electrical wiring to mounting the charger, we ensure a seamless installation that meets manufacturer specifications.

Step 3 - Pay

After installation, testing, commissioning and user training we will send an invoice where you can pay upfront or in monthly instalments subject to our finance plans.

Explore Our Services

Proudly delivering renewable energy solutions for domestic and commercial clients in Beds, Herts and Bucks since 2009

Solar Panel Installation

At MJ Renewables, we specialise in professional solar panel installation services across Beds, Herts and Bucks. Whether you're a homeowner or a business looking to harness the power of solar energy, our experienced team is here to help you every step of the way.

Battery Storage For Solar Panels

Enhance the efficiency and reliability of your solar energy system with battery storage solutions from MJ Renewables. Serving Beds, Herts and Bucks, we offer expert installation and integration of battery storage systems to maximise your energy independence.

Ground Mounted Solar Panel Installation

MJ Renewables offers expert installation services for ground-mounted solar panels in Beds, Herts and Bucks. Ground-mounted solar panels are an excellent option for properties with ample space or where roof installation is not feasible.

EV Charger Installation

MJ Renewables offers professional EV charger installation services across Beds, Herts and Bucks. Whether you're a homeowner or a business looking to accommodate electric vehicles, we provide reliable and efficient solutions tailored to your needs.